Air Products Turnaround
Location
Carson, CA
Carson, CA
Timeline
January – November 2020
January – November 2020
Owner/General Contractor
Air Products & Chemicals, Inc.
Air Products & Chemicals, Inc.
Project Description
- Erected 150’H scaffold around flare for tip replacement.
- 64 scaffold builders and 20 insulators on-site working around-the-clock for seven 12-hour days.
- Overcame project delays due to the Covid-19 outbreak to complete the project on time.